Monday, 25 January 2016

Prep for the Slab

Site scrape started on the 18th Jan...woo hoo!!!
We also had about 20 piers put in for the reinforcement for the slab.
They also started the electrical on Thursday 21st.
They expect to pour the slab 4th February...it's really happening now.